Market data loadingS&P 500--NASDAQ--Data as of latest ETNo timestamp

NextDecade Corporation (NEXT) SEC Filings & Earnings Calls

EquiReason read 15 NextDecade Corporation SEC filings in the last 12 months. Latest: 8-K on 2026-10-01 — Director Giovanni Oddo resigned from board; no disagreement with company. Replacement right held by affiliate Mubadala. Routine board change..

Source: SEC EDGAR filings · figures as of 2026-06-30 · read by EquiReason

NEXTNextDecade CorporationFollow NEXT — free
Oil & Gas Equipment & Services · Energy
—
Price chart with a free account
Market cap
1.7B
P/E TTM
—
Dividend yield
—
52-week
—
Next earnings
29 Oct, in 5 days

Every filing, read

last 12 months · SEC

What happened, the numbers inside, guidance and risks. The original is one click away.

1 Oct 20268-K · 5.02Director Giovanni Oddo resigned from board; no disagreement with company. Replacement right held by affiliate Mubadala. Routine board change.SEC ↗
30 Jul 202610-QNextDecade reported Q2 2026 results: construction progress on 5 LNG trains, raised $2.4B in debt and $760M in equity, and filed for Train 6 expansion.open

Figures in the filing · each found in the filing text

Capital expenditure · H1-2026$2.16B+44% y/y
Cash and cash equivalents · 2026-06-30$84M
Restricted cash · 2026-06-30$416M
Debt, net · 2026-06-30$10.42B
Net loss attributable to common stockholders · Q2-2026$-65M+8% y/y
Overall completion percentage Trains 1 and 2 · 2026-06-3074.0%
Overall completion percentage Train 3 · 2026-06-3050.4%
Overall completion percentage Train 4 · 2026-06-3015.5%
Overall completion percentage Train 5 · 2026-06-309.4%

Guidance

First LNG production from Train 1 expected in first half of 2027

Management reaffirmed first LNG production timeline and continues to advance construction and expansion plans.

Risks flagged

Project execution risk

“Our progress in the development of our natural gas liquefaction and liquefied natural gas (“LNG”) export project and the timing of that progress” · word for word

Financing risk

“Our ability to secure additional debt and equity financing in the future, including any refinancing of outstanding indebtedness, on commercially acceptable terms” · word for word

Debt service burden

“the ability to generate sufficient cash flow to satisfy our and our subsidiaries’ significant debt service obligations or to refinance such obligations ahead of their maturity” · word for word
Read the original on SEC EDGAR ↗
2 Jul 20268-K · 1.01, 2.03Item 2.03 indicates creation of a direct financial obligation;open

Risks flagged

Increased leverage from $3.5B debt issuance, though proceeds used to repay existing debt, so net leverage impact may be neutral.

“RGLNG intends to use net proceeds to repay a portion of outstanding borrowings under existing credit agreements.”
Read the original on SEC EDGAR ↗
18 Jun 20268-K · 1.01, 2.03NextDecade Corporation filed an 8-K for entering a material definitive agreement and creating a direct financial obligation;open

Risks flagged

Additional debt increases leverage, but proceeds used to pay down existing debt, so net impact may be neutral.

“Proceeds used primarily to make an equity contribution to RGLNG to reduce outstanding borrowings under its credit facilities.”
Read the original on SEC EDGAR ↗
10 Jun 2026SC 13DGeneral Atlantic entities filed Schedule 13D disclosing $100M in convertible loans and warrants to NextDecade, with board designation rights, supporting LNG project financing.open

Figures in the filing · each found in the filing text

Warrant shares8,386,255

Risks flagged

Project financing dependency

“The Credit Agreement includes covenants that, among other things, limit the ability of Super Holdings to incur additional indebtedness, make certain investments or pay dividends or distributions on equity interests or subordinated indebtedness or purchase, redeem, or retire equity interests, sell or transfer assets, incur liens or dissolve, liquidate, consol” · word for word
Read the original on SEC EDGAR ↗
10 Jun 2026SC 13DGeneral Atlantic entities filed Schedule 13D disclosing $100M in convertible loans and warrants to NextDecade, with board designation rights, supporting LNG project financing.open

Figures in the filing · each found in the filing text

Warrant shares8,386,255

Risks flagged

Project financing dependency

“The Credit Agreement includes covenants that, among other things, limit the ability of Super Holdings to incur additional indebtedness, make certain investments or pay dividends or distributions on equity interests or subordinated indebtedness or purchase, redeem, or retire equity interests, sell or transfer assets, incur liens or dissolve, liquidate, consol” · word for word
Read the original on SEC EDGAR ↗
3 Jun 20268-K · 5.02Reported a director or officer change (departure, election, appointment or pay arrangement)SEC ↗
1 May 202610-QPhase 1 completion percentage 67.8; Train 3 completion percentage 44.2; Train 4 completion percentage 10.6open

Figures in the filing · each found in the filing text

Phase 1 completion percentage · Phase 1 · Q1-202667.8%
Train 3 completion percentage · Train 3 · Q1-202644.2%
Train 4 completion percentage · Train 4 · Q1-202610.6%
Train 5 completion percentage · Train 5 · Q1-20266.8%
Capital expenditure · Q1-2026$1.18B+53% y/y
Net loss · Q1-2026$-195M-21% y/y
Cash and cash equivalents · 2026-03-31$143M
Restricted cash · 2026-03-31$322M
Debt, net · 2026-03-31$9.36B
Equity commitments received · Q1-2026$249M+16% y/y

Risks flagged

Construction cost overrun risk

“Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion.” · word for word

Debt service burden

“Interest expense $79,247 for Q1 2026 vs $27,205 for Q1 2025, +191% YoY.”

No revenue yet

“Revenues $0 for Q1 2026 and Q1 2025.”
Read the original on SEC EDGAR ↗
23 Apr 2026DEF 14AProxy statement for annual meeting, including director elections, equity plan amendment, advisory vote on executive compensation, and ratification of auditors.open

Figures in the filing · each found in the filing text

Phase 1 Construction Progress · Rio Grande LNG Facility · 2025-12-3158.0%
Total Recordable Incident Rate · 2025-01-01 to 20$0.22
Project Financing Closed for Trains 4 and 5 · 2025-01-01 to 20$13.40B
Annual Incentive Payout Factor · 2025-01-01 to 20157.0%
2022-2025 PSU Payout · 2022-09-01 to 2014.3%
Number of Employees · 2025-12-31370
Shares Outstanding · 2026-04-15264,979,673

Risks flagged

Regulatory and Legal Risk

“Pursued appellate and regulatory avenues to ensure construction at the Rio Grande LNG Facility could continue uninterrupted after an adverse ruling by the U.S. Court of Appeals for the D.C. Circuit (D.C. Circuit Court) in August 2024 and provided information to FERC to facilitate additional environmental review of the first five trains at the Rio Grande LNG ” · word for word

Project Execution Risk

“Advanced the construction of Phase 1 (Trains 1-3) at the Rio Grande LNG Facility safely, on budget, and ahead of schedule” · word for word

Financing Risk

“Closed a total of approximately $13.4 billion in project financing transactions to fully fund the expected construction costs of Trains 4 and 5” · word for word
Read the original on SEC EDGAR ↗
15 Apr 20268-K · 5.02Reported a director or officer change (departure, election, appointment or pay arrangement)SEC ↗
2 Mar 202610-KProject completion percentage - Trains 1&2 and common facilities 64.5; Project completion percentage - Train 3 39.8; Project completion percentage - Train 4 7.8; Guidance: First LNG production from Train 1 expected in first half of 2027open

Figures in the filing · each found in the filing text

Project completion percentage - Trains 1&2 and common facilities · Phase 1 · January 202664.5%
Project completion percentage - Train 3 · Phase 1 · January 202639.8%
Project completion percentage - Train 4 · Train 4 · January 20267.8%
Project completion percentage - Train 5 · Train 5 · January 20263.3%
LNG production capacity - Train 4 · Train 4 · FY20256
LNG production capacity - Train 5 · Train 5 · FY20256
Total project cost - Train 4 · Train 4 · FY2025$6.70B
Total project cost - Train 5 · Train 5 · FY2025$6.70B
Cash, cash equivalents and restricted cash · FY2025$707M+80% y/y
Net loss attributable to common stockholders · FY2025$-306M+396% y/y

Guidance

First LNG production from Train 1 expected in first half of 2027

Company expects first LNG production in first half of 2027, with early cargo marketing achieving margins over $3.00/MMBtu. Multiple FIDs and project financings closed, indicating strong execution and demand.

Risks flagged

Construction delay risk

“Progress on Train 4 as of January 2026 is in line with the EPC contract. Since FID of Train 4 in September 2025, progress has been focused primarily on engineering drawings and issuance of purchase requisitions for key equipment, and soil stabilization in the Train 4 area has commenced.” · word for word

Financing risk for future trains

“We intend to fund development activities and general and administrative expenses for the foreseeable future with our cash and cash equivalents on hand, the services fee due in September 2026 and through the sale of additional equity, equity-based or debt securities in us or in our subsidiaries. There can be no assurance that we will succeed in selling such s” · word for word

Regulatory and legal risk

“In December 2025, certain intervenors petitioned the D.C. Circuit Court to review the order on remand, and their request remains pending.” · word for word

Geopolitical risk

“The Russia-Ukraine conflict, conflict in the Middle East and other sources of volatility in the energy markets may materially and adversely affect our business, financial condition, operating results, cash flow, liquidity and prospects, including our efforts to reach a final investment decision with respect to the Rio Grande LNG Facility.” · word for word
Read the original on SEC EDGAR ↗
11 Dec 2025SC 13D/ASchedule 13D/A: HGC NEXT INV LLC 9.7%SEC ↗
20 Nov 2025SC 13D/ASchedule 13D/A: HGC NEXT INV LLC 8.8%SEC ↗
18 Nov 20258-K · 1.01, 2.03, 3.02Entered a material definitive agreement (acquisition, partnership, or major contract); took on a material direct financial obligation, increasing leverageopen

Risks flagged

Insufficient information to assess risk.

Read the original on SEC EDGAR ↗
30 Oct 202510-QNextDecade achieved FID on Train 4 (Sep 2025) and Train 5 (Oct 2025), signed multiple 20-year LNG SPAs, and satisfied the FERC Remand Condition, significantly advancing its Rio Grande LNG project.open

Figures in the filing · each found in the filing text

Rio Grande LNG Facility under construction · Q3-2025$8.46B
Cash and cash equivalents · Q3-2025$209M
Restricted cash · Q3-2025$535M
Debt, net · Q3-2025$6.61B
Capital expenditure · 9M-2025$2.86B+53% y/y
Net loss attributable to common stockholders · 9M-2025$-259M

Risks flagged

FERC Regulatory Delay Risk

“The effectiveness of the Contingent Swaps remains contingent upon the issuance by FERC of a final remand order that is not subject to further appeal (the “FERC Remand Condition”). As of September 30, 2025, the Contingent Swaps had not yet become effective.” · word for word

Construction Cost Overrun Risk

“Total project costs for Train 4 and related infrastructure are expected to total approximately $6.7 billion.” · word for word

Interest Rate Exposure

“Interest expense, net $94,670 (9M 2025) vs $67,414 (9M 2024), +40% YoY.”
Read the original on SEC EDGAR ↗

NextDecade Corporation — questions

What did NextDecade Corporation file recently?
15 SEC filings in the last 12 months. Latest: 8-K on 2026-10-01 — Director Giovanni Oddo resigned from board; no disagreement with company. Replacement right held by affiliate Mubadala. Routine board change.

Every figure on this page comes from NextDecade Corporation's own SEC filings — see them on SEC EDGAR. Price data is licensed and shown only inside the product.

How these figures are read: methodology · EquiReason.