Fermi Inc. (FRMI) SEC Filings & Earnings Calls

EquiReason read 33 Fermi Inc. SEC filings in the last 12 months. Latest: 8-K on 2026-10-16 — Fermi Inc. subsidiary entered into a Limited Waiver and Amendment to Equipment Supply Loan Financing Agreement with MUFG, eliminating a 400 MW lease/offtake covenant and associated.

Source: SEC EDGAR filings · figures as of 2026-06-30 · read by EquiReason

FRMIFermi Inc.Follow FRMI — free
REIT - Specialty · Real Estate
—
Price chart with a free account
Market cap
1.6B
P/E TTM
—
Dividend yield
—
52-week
—
Next earnings
12 Nov, in 19 days

Every filing, read

last 12 months · SEC

What happened, the numbers inside, guidance and risks. The original is one click away.

16 Oct 20268-K · 8.01Fermi Inc. subsidiary entered into a Limited Waiver and Amendment to Equipment Supply Loan Financing Agreement with MUFG, eliminating a 400 MW lease/offtake covenant and associated potential principal payments of ~$22M in Q4 2026, ~$19M inopen

Figures in the filing · each found in the filing text

amendment fees · Q4-2026$25M

Risks flagged

Debt covenant waiver indicates potential financial strain; $25M fee is a cash outflow

“Amendment eliminates covenant requiring lease/offtake for 400 MW; paid $25M fees”
Read the original on SEC EDGAR ↗
14 Oct 20268-K · 7.01Fermi Inc. disclosed a binding 15-year lease with TensorWave for 222 MW total power capacity, with $6.5B in phase one contracted revenue, backed by AMD credit support. Estimated NOI margin 75-80%.open

Figures in the filing · each found in the filing text

Phase one contracted revenue · TensorWave lease · 15-year initial $6.50B
Total power capacity · TensorWave lease · phase one222
Critical IT capacity · TensorWave lease · phase one156

Risks flagged

Construction and permitting risks for large-scale data center and power generation assets.

“risks associated with large-scale construction and infrastructure development; interconnection availability and grid constraints” · word for word

Counterparty risk: TensorWave is a private, fast-growing AI cloud with $350M Series B; credit support from AMD mitigates but not eliminates risk.

“Credit support agreement with investment-grade AMD; ends early if TensorWave or its guarantor holds an investment-grade rating for 12 consecutive months” · word for word

Regulatory and permitting risks, including NRC and TCEQ approvals.

“our ability to obtain and maintain required permits and regulatory approvals, including from the NRC and TCEQ”
Read the original on SEC EDGAR ↗
2 Oct 2026DEF 14AFermi's CEO was removed for cause and CFO resigned, with ongoing litigation and a proxy contest, creating significant governance and execution risk.open

Risks flagged

Leadership and Governance Risk

“Toby R. Neugebauer served as Co-Founder and Chief Executive Officer of the Company from its inception until April 17, 2026, when he was removed from the role of CEO by the Board. On April 30, 2026, Mr. Neugebauer's employment was terminated for cause.” · word for word

Litigation Risk

“On May 1, 2026, our former CEO, Mr. Neugebauer, filed a verified petition and application for temporary restraining order and temporary injunction in the Business Court of the State of Texas, First Division, captioned Neugebauer v. Fermi Inc., et al.” · word for word

Project Execution Risk

“our business model is highly dependent on the successful construction, development, leasing, and continued maintenance of Project Matador” · word for word
Read the original on SEC EDGAR ↗
31 Aug 20268-K · 5.08, 8.01Fermi Inc. announced appointment of Lee McIntire as CEO effective August 11, 2026, and subsequent Audit Committee changes.SEC ↗
14 Aug 20268-K · 5.02CEO Base Salary $750,000.00; CEO Target Bonus Percentage 100; CEO RSU Award Value $3Mopen

Figures in the filing · each found in the filing text

CEO Base Salary · point_in_time$750000.00
CEO Target Bonus Percentage · point_in_time100.0%
CEO RSU Award Value · point_in_time$3M

Risks flagged

CEO change may signal strategic shift; no performance metrics disclosed.

“Appointment of new CEO; no discussion of prior performance or transition reasons.”
Read the original on SEC EDGAR ↗
14 Aug 202610-QQuarterly report for pre-revenue AI data center developer; no material change in operations.open

Figures in the filing · each found in the filing text

Net proceeds from offering · Q2-2026$35M

Risks flagged

Pre-revenue with no operating history

“We were formed in January 2025 and have not generated revenue to date.” · word for word

Substantial debt and liquidity risk

“Our business may not generate cash flow from operations in the future sufficient to service our debt and make necessary capital expenditures.” · word for word

Dilution risk from convertible notes

“Conversion of the Notes may dilute the ownership interest of our shareholders or may otherwise depress the price of our common stock.” · word for word

REIT election deferred indefinitely

“We have determined to defer our REIT election. ... It is possible that we will never make a REIT election.” · word for word
Read the original on SEC EDGAR ↗
13 Aug 20268-K · 2.02Anchor Customer Contract Value $6.50B; Anchor Customer Capacity 222; Capital Raised $431Mearningsopen

Figures in the filing · each found in the filing text

Anchor Customer Contract Value · TensorWave · Q2-2026$6.50B
Anchor Customer Capacity · TensorWave · Q2-2026$222.00
Capital Raised · Q2-2026$431M
Hillcore Alliance Capacity · Hillcore · Q2-2026$2600.00
Total Site Capacity (with Hillcore) · Project Matador · Q2-2026$4800.00
Landed Power Assets · Q2-2026$1500.00

Risks flagged

Project execution risk; construction and regulatory approvals needed for power generation.

“Path to first power subject to binding customer agreements and approvals.”

Customer concentration risk; first anchor customer is TensorWave.

“First anchor customer agreement with TensorWave.”

Financing risk; future capital needs for buildout.

“Hillcore alliance requires no capital from Fermi, but future phases may need additional funding.”
Read the original on SEC EDGAR ↗
23 Jul 20268-K · 5.02Annualized base salary $500,000.00; Target annual bonus 100; Maximum annual bonus 200open

Figures in the filing · each found in the filing text

Annualized base salary · executive_compensation · FY2026$500000.00
Target annual bonus · executive_compensation · FY2026100.0%
Maximum annual bonus · executive_compensation · FY2026200.0%
Severance · executive_compensation · FY2026$18.00
LTIP award grant date value · executive_compensation · FY2026$2M
Sign-on equity award RSUs · executive_compensation · FY20261,500,000

Risks flagged

Key person dependency risk due to new executive appointments; potential integration and performance risk.

“Appointment of multiple new officers including CFO, COO, CCO, and General Counsel with significant compensation packages.”
Read the original on SEC EDGAR ↗
15 Jul 20268-K · 1.01, 2.03, 3.02, 7.01Fermi Inc. issued $375M aggregate principal of 5.00% convertible senior notes due 2031, plus $56.25M greenshoe exercised, total gross proceeds $431.25M. Net proceeds ~$416.81M after fees. Used ~$34.5M for capped call transactions; remainderopen

Figures in the filing · each found in the filing text

aggregate principal amount of notes · Q3-2026$431M
net proceeds · Q3-2026$417M
cost of capped call transactions · Q3-2026$35M

Risks flagged

Convertible debt increases leverage and interest expense; potential dilution if stock price exceeds conversion price.

“Notes bear 5.00% interest, convertible into shares; capped calls only partially offset dilution up to $14.64.”
Read the original on SEC EDGAR ↗
13 Jul 20268-K · 5.02Reported the departure of a director or principal officer (CEO/CFO change); filed financial statements and exhibits with this reportopen

Risks flagged

Governance risk from board disagreement and potential control issues.

“Director resignation due to disagreement over access to books and records and delegation of financing oversight.”
Read the original on SEC EDGAR ↗
9 Jul 20268-K · 7.01, 8.01Aggregate principal amount of convertible senior notes $350Mopen

Figures in the filing · each found in the filing text

aggregate principal amount of convertible senior notes · Q2-2026$350M

Risks flagged

Potential dilution from convertible notes and uncertainty around REIT election.

“Convertible notes may convert to equity; REIT election deferred with no assurances.”
Read the original on SEC EDGAR ↗
8 Jul 2026SC 13D/ACaddis Holdings and Griffin Perry filed an amended Schedule 13D correcting a clerical error, disclosing an 8.2% beneficial ownership stake in Fermi Inc. and reaffirming support for the board and management.open

Figures in the filing · each found in the filing text

Beneficial Ownership · 2026-06-3052,256,833
Read the original on SEC EDGAR ↗
8 Jul 2026SC 13D/ACaddis Holdings and Griffin Perry filed an amended Schedule 13D correcting a clerical error, disclosing an 8.2% beneficial ownership stake in Fermi Inc. and reaffirming support for the board and management.open

Figures in the filing · each found in the filing text

Beneficial Ownership · 2026-06-3052,256,833
Read the original on SEC EDGAR ↗
2 Jul 2026SC 13D/ACo-founder Caddis Holdings and Perry Griffin file amended 13D reaffirming support for Fermi Inc. board and strategy, with 8.2% stake.open

Figures in the filing · each found in the filing text

Beneficial Ownership · 2026-07-0252,318,073
Percent of Class · 2026-07-028.2%
Read the original on SEC EDGAR ↗
2 Jul 2026SC 13D/ACo-founder Caddis Holdings and Perry Griffin file amended 13D reaffirming support for Fermi Inc. board and strategy, with 8.2% stake.open

Figures in the filing · each found in the filing text

Beneficial Ownership · 2026-07-0252,318,073
Percent of Class · 2026-07-028.2%
Read the original on SEC EDGAR ↗
15 May 2026SC 13DInitial Schedule 13D filed by co-founder Caddis Holdings disclosing 9.1% stake and public support for Fermi's board and strategic plan; no activist intent.open

Risks flagged

No material risk signals identified in this filing.

Read the original on SEC EDGAR ↗
15 May 202610-QCEO terminated for cause, CFO resigned, interim leadership appointed amid going concern riskopen

Figures in the filing · each found in the filing text

Net loss · Q1-2026$-189M
Cash and cash equivalents · 2026-03-31$208M
Restricted cash · 2026-03-31$36M
Capital expenditures (property, plant and equipment) · Q1-2026$441M
General and administrative expenses · Q1-2026$166M
Share-based compensation expense · Q1-2026$134M
Net cash used in operating activities · Q1-2026$-7M
Net cash provided by financing activities · Q1-2026$283M
Undrawn committed borrowing capacity (Yorkville Note) · 2026-03-31$156M

Risks flagged

Going concern risk

“these conditions raise substantial doubt about the Company’s ability to continue as a going concern within that period” · word for word

No revenue and no tenant agreements

“We have not yet entered into a lease agreement with a tenant” · word for word

Massive capex commitments without funding

“the incremental capital expenditures we will incur to complete the development of Phase 0 and Phase 1 of Project Matador could exceed $3 billion in the aggregate” · word for word

Management turmoil

“Toby Neugebauer was removed by the Company’s Board of Directors from the positions of President and Chief Executive Officer” · word for word

High leverage and debt covenants

“The Credit Agreement imposes loan-to-value requirements on the collateral” · word for word
Read the original on SEC EDGAR ↗
15 May 2026SC 13DInitial Schedule 13D filed by co-founder Caddis Holdings disclosing 9.1% stake and public support for Fermi's board and strategic plan; no activist intent.open

Risks flagged

No material risk signals identified in this filing.

Read the original on SEC EDGAR ↗
14 May 20268-K · 2.02Total cash and restricted cash $243M; new equipment finance facilities $785M; net loss $-189Mearningsopen

Figures in the filing · each found in the filing text

total cash and restricted cash · Q1-2026$243M
new equipment finance facilities · Q1-2026$785M
net loss · Q1-2026$-189M
capital invested in property, plant, and equipment · Q1-2026$441M
outstanding debt · Q1-2026$421M

Risks flagged

Net loss driven by non-cash items; high cash burn rate.

“$189M net loss; $441M capex; reliance on financing for liquidity.”
Read the original on SEC EDGAR ↗
6 May 20268-K · 7.01Issued a Regulation FD disclosure (forward guidance or material update); filed financial statements and exhibits with this reportopen

Risks flagged

Activist risk from former CEO seeking board control and potential sale of company.

“Former CEO filed SEC filings to call special meeting and solicit consents to take control of board.”
Read the original on SEC EDGAR ↗
5 May 20268-K · 5.02Reported a director or officer change (departure, election, appointment or pay arrangement)open

Risks flagged

No material risk; routine board appointment.

“Appointment to fill vacancy; no compensation changes.”
Read the original on SEC EDGAR ↗
30 Apr 202610-K/ACEO terminated for cause and CFO resigned, with interim leadership established via Office of the CEO.open

Figures in the filing · each found in the filing text

Shares Outstanding · 2026-04-26637,574,239
Unvested RSUs · 2025-12-3138,412,070
Shares Available for Future Issuance · 2025-12-3173,900,580
CEO Base Salary · FY2025$500000.00
Non-CEO NEO Base Salary · FY2025$500000.00
Non-CEO NEO Target Bonus Percentage · FY2025200.0%
Non-CEO NEO Annual LTI Target Percentage · FY2025200.0%
CEO Severance Multiple · FY20252
Non-CEO NEO Severance Multiple · FY20252
CEO Top-Up Grant Percentage · FY202540.0%

Risks flagged

Executive leadership vacuum

“Mr. Neugebauer was removed from his role as the Company’s Chief Executive Officer, effective April 17, 2026... Mr. Everson resigned from his position as the Company’s Chief Financial Officer and Secretary, effective April 19, 2026” · word for word

CEO termination for cause

“On April 30, 2026, the Company terminated Mr. Neugebauer’s employment for Cause pursuant to his Employment Agreement as a result of conduct in violation of the terms of such agreement and of Company policies.” · word for word

Massive equity dilution potential

“Number of securities to be issued upon exercise of outstanding options, warrants and rights (A) 38,412,070... Number of securities remaining available for future issuance under equity compensation plans (C) 73,900,580” · word for word

Related party governance risk

“In 2025, we paid TFCU $1,332,177 under the Services Agreement, including a $750,000 discretionary bonus in connection with our initial public offering.” · word for word

High executive compensation commitments

“an amount equal to two (2) times the sum of (1) the NEO’s base salary... and (2) the NEO’s target Annual Bonus” · word for word
Read the original on SEC EDGAR ↗
30 Apr 20268-K · 5.02Reported the departure of a director or principal officer (CEO/CFO change); filed financial statements and exhibits with this reportopen

Risks flagged

Interim CFO appointment may indicate instability in finance leadership; no permanent successor named.

“Appointed as Interim CFO until a permanent successor is named.”
Read the original on SEC EDGAR ↗
20 Apr 20268-K · 5.02, 7.01Reported the departure of a director or principal officer (CEO/CFO change); issued a Regulation FD disclosure (forward guidance or material update)open

Risks flagged

CEO and CFO departures create leadership vacuum; interim CFO search underway.

“Toby Neugebauer departed as CEO; Miles Everson resigned as CFO; interim CFO search underway.”

Project Matador lease agreement milestones may be extended; discussions ongoing.

“TTUS is actively engaged in good-faith discussions to extend certain milestones in the lease agreement as we advance Project Matador into its next phase.”
Read the original on SEC EDGAR ↗
17 Apr 20268-K · 5.02Reported the departure of a director or principal officer (CEO/CFO change); filed financial statements and exhibits with this reportopen

Risks flagged

Leadership vacuum and potential strategic drift during CEO search.

“CEO departure without permanent successor; interim leadership may lack full authority.”
Read the original on SEC EDGAR ↗
30 Mar 202610-KAnnual report filed by development-stage company with no revenue, significant capital needs, and early-stage progress on permitting and equipment procurement for a large-scale AI data center power campus.open

Figures in the filing · each found in the filing text

Secured generation capacity (combined cycle) · FY2025$2.50B
Simple cycle capacity under control · FY2025$1.50B
Grid-supplied capacity secured · FY2025$200M
Site acreage · FY2025$7570.00
Phase 0/1 estimated total capital expenditure · FY2025$3.00B

Risks flagged

No operating history or revenue

“We have not generated any revenue to date and do not expect to do so until the first subleases of our powered shells and the delivery of on-demand energy commence, which we expect will not occur until the first half of 2027.” · word for word

No binding tenant contracts

“We have not yet constructed our facilities or entered into any binding contracts with any tenants, and there is no guarantee that we will be able to do so in the future.” · word for word

Significant capital requirements

“We will require significant additional capital to construct and complete Project Matador, and we may not be able to secure such financing on time with acceptable terms, or at all.” · word for word

Material weakness in internal controls

“We have identified a material weakness in our internal control over financial reporting.” · word for word

Execution risk on large-scale multi-phase development

“Project Matador is an unprecedented, large-scale, multi-phase development effort that presents significant planning, execution, and coordination risks.” · word for word
Read the original on SEC EDGAR ↗
30 Mar 20268-K · 2.02Capital raised $1.80B; Capitalized PP&E $935M; Campus acreage 7,570; Guidance: $935M capitalized in FY2025earningsopen

Figures in the filing · each found in the filing text

Capital raised · FY2025$1.80B
Capitalized PP&E · FY2025$935M
Campus acreage · FY20257,570
Perimeter fencing · FY2025$11.30
Gas pipeline · FY2025$4.60
Water lines · FY2025$7.20
Water supply capacity · FY2025$18.50
Generation pipeline capacity · FY2025$11.00
Potential campus footprint · FY20257,570

Guidance

$935M capitalized in FY2025

Strong execution on capex and infrastructure build; no explicit forward guidance but tone is highly positive.

Risks flagged

Execution risk on massive infrastructure project; reliance on partnerships and financing.

“Project Matador still under construction; subject to permitting, financing, interconnection.”

Concentration risk on single site and AI energy demand.

“Campus dependent on AI data center demand; single location in Texas Panhandle.”
Read the original on SEC EDGAR ↗
27 Mar 20268-K · 1.01, 2.03Fermi Inc. entered into an Equipment Supply Loan Financing Agreement on March 26, 2026, creating a direct financial obligation. No dollar amount stated.open

Risks flagged

New debt obligation may increase financial leverage; terms undisclosed.

“Creation of a Direct Financial Obligation or an Obligation under an Off-Balance Sheet Arrangement of a Registrant.” · word for word
Read the original on SEC EDGAR ↗
25 Feb 20268-K · 1.01, 2.03Fermi Inc. enters Master Loan Agreement for Fermi High Voltage Warehouse LLC, increasing leverage via a credit facility.open

Risks flagged

Increased leverage from new debt obligation may strain liquidity.

“Master Loan Agreement dated February 19, 2026, among Fermi High Voltage Warehouse LLC and lenders.”
Read the original on SEC EDGAR ↗
10 Feb 20268-K · 1.01, 2.03, 7.01Fermi Inc. secured a $500 million non-recourse equipment loan from MUFG to fund turbine acquisition and project development for its 11GW private energy campus, strengthening near-term execution certainty.open

Figures in the filing · each found in the filing text

equipment loan amount · 2026-02-10$500M
total controlled generation capacity · 2026-02-10$2.00
total campus capacity · 2026-02-10$11.00

Risks flagged

Execution risk on large-scale energy project; reliance on financing and turbine delivery timeline.

“Turbine deliveries beginning as early as 1H 2026; project financing still needed for full scale.” · word for word
Read the original on SEC EDGAR ↗
12 Dec 20258-K · 8.01AICA amount $150Mopen

Figures in the filing · each found in the filing text

AICA amount · 2025-11-03$150M

Risks flagged

Key tenant contract terminated; project timeline and revenue uncertainty increased.

“First Tenant terminated the AICA; exclusivity period expired; no definitive lease agreement yet.”
Read the original on SEC EDGAR ↗
12 Nov 202510-QFermi Inc. filed a 10-Q as a development-stage company with no revenue, significant capital needs, and a material weakness in internal controls.open

Risks flagged

Development-stage company with no revenue

“We are a development-stage company with no operating history or historical revenue, and we face execution risk across all major components of our business.” · word for word

Significant capital requirements

“We currently estimate that the total capital expenditures we will incur to complete the development of Phase 0 and Phase 1 of Project Matador could exceed $2 billion in the aggregate.” · word for word

No binding tenant agreements

“We have not yet constructed our facilities or entered into any binding contracts with any tenants, and there is no guarantee that we will be able to do so in the future.” · word for word

Material weakness in internal controls

“We have identified a material weakness in our internal control over financial reporting.” · word for word

Technology obsolescence risk

“Technological advances or disruptive innovations, specifically advancements in AI, may outpace our development cycle, and we are exposed to technology obsolescence across all major asset classes.” · word for word
Read the original on SEC EDGAR ↗
10 Nov 20258-K · 2.02, 7.01Planned total generation capacity 11,000; Capital raised year-to-date $1.60B; Target first power delivery 1,100earningsopen

Figures in the filing · each found in the filing text

Planned total generation capacity · Q3-2025$11000.00
Capital raised year-to-date · FY2025$1.60B
Target first power delivery · 2026$1100.00

Risks flagged

Execution risk on large-scale infrastructure project.

“Project Matador is a first-of-its-kind complex; delays or cost overruns possible.”

Regulatory and permitting risk for nuclear component.

“Fermi is the only American company with an accepted COL permit under review for new clean nuclear power.” · word for word
Read the original on SEC EDGAR ↗

Fermi Inc. — questions

What did Fermi Inc. file recently?
33 SEC filings in the last 12 months. Latest: 8-K on 2026-10-16 — Fermi Inc. subsidiary entered into a Limited Waiver and Amendment to Equipment Supply Loan Financing Agreement with MUFG, eliminating a 400 MW lease/offtake covenant and associated potential principal payments of ~$22M in Q4 2026, ~$19M in

Every figure on this page comes from Fermi Inc.'s own SEC filings — see them on SEC EDGAR. Price data is licensed and shown only inside the product.

How these figures are read: methodology · EquiReason.